EIA Reports Related to HZMB
Supplementary Information on comparison between Alignment Options A & C
for
the middle section of HKLR
(1) Introduction
(1.1) This
Paper is to respond to ACE EIA-Subcommittee’s request for a detailed comparison
on environmental aspects between Alignment Options A and C as presented in the
EIA Report for the middle section of Hong Kong Link Road. (The section of HKLR between San Shek
Wan/Airport-west and Tung Chung/Airport-east is referred to as the middle
section in this Paper. Three
alignment options have been presented in the EIA Report viz. Options A, B and
C, as shown on the attached Figure 1.)
(1.2) As
pointed out in the EIA Report, Option C involves a tunnel with an eastern
portal that will encroach upon the Lantau North (Extension) Country Park. It was considered that this
should amount to a vital factor for concluding the option as not feasible, as
there is a feasible alternative (Option A) that could avoid such encroachment
upon the Country Park.
(1.3) After
the presentation at the ACE EIA Sub-Committee Meeting on 21.9.09, it was
requested that a more detailed comparison be made between Options A and C on
environmental aspects.
(2) Relevant
Key Aspects of Option A (Total length approximately 12.1km)
(2.1) Option
A takes the form of a viaduct structure (i.e. trestle-bridge) along the Airport
Channel on the southern side of the Airport Island. At the western end of the Channel, the
HKLR will run along the Lantau side in order to avoid the critical aviation zone
around the runway-tip and to avoid affecting the Government Flying Service (GFS) operations. The spans of
this portion of HKLR viaduct will be designed to ensure that the viaduct
structure will overpass the headland between San Shek Wan & Sha Lo Wan, without
any physical contact. The overall layout of Option A is shown on Figure 2.
(2.2) The
HKLR viaduct will cross the Airport Channel to run along the Airport side as
soon as practicable after avoiding the zone critical to the operations of the
runway and the GFS.
(2.3) The
layout of Option A is shown at a finer level on Figures 3 to 4, which also highlights relevant key aspects
including the following:
(a) As
shown in Inset X on Figure 4, the portion of Option A
at/near the western end of the Airport Channel will be designed with larger
spans, not only to overpass the San Shek Wan/Sha Lo Wan headland, but also to
reduce the number of columns facing Sha Lo Wan. The span-arrangement
will also ensure that HKLR could overpass the Sha Lo
Wan Pier. A large span is required too for crossing the navigation within the Airport Channel.
(b) The
spans of the aforesaid portion of HKLR will be of the order of 100m to 180m,
and are envisaged to take the in-situ balanced-cantilever bridgeform with
haunches. Such spans are
substantially larger than spans for the more common precast-segmental
bridgeform without haunches, which are practicably up to approximately 75m. A comparison of the two bridgeforms
noted above is shown in elevation on Figure
4. After crossing the Airport
Channel, the columns of HKLR under Option A will run along the seawall of the
Airport Island. As shown in Inset Y on Figure 4, these columns will all be located above the high water
mark.
(c) To
summarise, the majority of the columns of the HKLR viaduct in the Airport
Channel are not in water. Only about 13 pairs[1]
of columns (for the portion of HKLR at/near Sha Lo Wan and across the Airport
Channel) are in the water.
(d) At/near
Sha Lo Wan, the relevant sensitive receivers are mainly the village houses as
shown on Figure 3. The majority of these village houses are
at least at 300m away from the Option A HKLR viaduct. For the remaining portion of
HKLR along the Airport Channel, there are no significant
sensitive receivers nearby, as the village houses (at Kau Liu/Tin Sam) are at approx. 400m
away.
(e) On western side of Lantau, the
Option A HKLR is at about 600m away from the village houses at San Shek Wan.
(3) Relevant
Key Aspects of Option C (Total length approximately 11.8km)
(3.1) Option
C takes the form of a tunnel through the Lantau hillside. The western portal is located near Sham
Wat in order to avoid the village
houses at San Shek Wan and Sha Lo Wan, whereas the location of the eastern
portal need to avoid the San Tau SSSI and the Hau Hok Wan horseshoe crab
breeding site as well as the village houses at Kau Liu/Tin Sam. The layout of Option C and other
relevant key aspects are shown on Figures
5 to 10.
(3.2) Before
entering the western portal, the Option C HKLR will take the form of a sea
viaduct similar to other portions of HKLR in the western waters. There is no fundamental difference
between Options A and C in this regard.
Similarly, on the eastern side, after daylighting from the eastern
tunnel portal the Option C HKLR will cross the Airport Channel as a viaduct
structure similar to the Option A channel-crossing as noted in (2.3) above.
(3.3) The
western portal will be about 300m away from the village houses at Sham Wat,
whilst the eastern portal will be about 250m to the village houses at Kau
Liu/Tin Sam.
(3.4) Relevant
key aspects on Option C as highlighted on Figures
6 to 10 include the following:
(a) As
shown in Figure 7, the western
portal will involve extensive cutting of the Lantau natural hillside because of the steep topography there. Such extensive cutting in order to form
a portal is essential for land tunnel
construction, as illustrated in photos shown on Figure 9 for portal-cuttings at construction stage, for various
tunnel projects in Hong Kong.
(b) Though
measures could be taken to apply extensive landscaping at the portal (see Figure 10 showing photos of completed landscaped portals
for various tunnel projects in Hong Kong), the landform will be altered
inevitably, i.e. loss of naturalness is inevitable.
(c) Similarly,
extensive cutting and loss of naturalness of the hillside are inevitable on the
eastern side too, for the eastern portal.
In addition, the eastern portal will inevitably encroach upon the Lantau
North (Extension) Country Park, in order to avoid the San Tau
SSSI and the Hau Hok Wan horseshoe crab breeding site. (Note: Though there is a small gap
between the Country Park boundary and the Lantau shoreline, the gap is
inadequate to accommodate the tunnel-portal plus its associated cutting. See cross-section on Figure 8 showing the above.) Furthermore, should the eastern portal
be located in that gap, its level would be too low to enable HKLR to across the
Airport Channel with adequate headroom for vessels.
(d) As
regards the main tunnelling work between the two portals, it will go through
rock strata for the majority of the tunnel length. For such a case, tunnel boring machine
(TBM) is not feasible not only because TBM usually requires a larger economy-of-scale
in view of the high mobilisation & set-up costs involved, but also because
HKLR is a dual-3 lane highway.
There is no TBM so far available in the
world capable of forming a bore through rock strata large enough for a dual-3
highway. If Option C is adopted,
the main tunnelling works will be constructed by the
drill-and-blast method, which is common for land tunnelling work. Drill-and-blast tunnelling in turn
requires processing of the blasted rocks, in order to bring the rocks to sizes
of suitable use. Such processing,
typically in the form of rock-crushing, will take place outside the tunnel, in
this case at both the eastern & western
portal sites.
(e) Another
special aspect for the Option C tunnel is that neither ends are accessible by
road. Conceivably, the only way to
dispose the tunnel-excavation materials is to convey them by conveyors/chutes
onto barges berthed against the Lantau shoreline right below the eastern and
western portal sites respectively.
As shown on Figure 10, the existing
seabed levels thereat are shallow. As a result, dredging will be required to
provide draught needed by the barges.
(For such construction barges, the draught required is approx. 4m. As shown on Figure 10 the seabed levels available here are approx. -2mPD only.)
(f) Another
important aspect for the design of a tunnel is the arrangement for exhaust of
traffic emissions within the tunnel.
It is envisaged that two ventilation shafts will be required for exhaust
of the traffic emissions. As shown
on Figure 6, since a large
proportion of the Option C tunnel is within the Country Park, it would be
inevitable for at least one of the ventilation shafts to encroach upon the
Country Park even if the ventilation system is designed to locate the ventilation shafts towards the western side as far as possible
to avoid the Country Park area.
(g) Furthermore, for practical reasons, hard shoulder cannot be provided within the
3.5km long tunnel for Option C.
This affects the traffic management and operation as well as emergency
handling for this important corridor.
(h) Basically, 24 hours ventilation
and lighting is required for the tunnel.
(4) Comparison
between Options A and C
(4.1) Air
Quality
(4.1.1) Operation Air
Quality Impact
(a) The
operation air quality impacts by Option A have been reported in the EIA
Report. For illustration, it should
be noted that the assessed 1-hour NO2 (a vital parameter for
operation air quality assessment for a highway project) at the Air Sensitive Receiver (ASR) at Sha Lo Wan is
246 µg/m³ for the highest case, at the Assessment Year of
2031. For this 246 µg/m³, approx. 17%
(i.e. 41 µg/m³) is due to emissions
from all road traffic; the remaining 205 µg/m³ being caused
by emissions from PRD, airport, power stations, and other non-traffic related
sources.
(b) For
Option C, the ASRs at Kau Liu/Tin Sam
village are subjected to impacts not only from the portion of HKLR open road
outside the eastern portal, but also emissions from the eastern portal
itself. (Note: Even if the tunnel
ventilation system is designed to emit tunnel-emissions via the shafts rather
than via the portals as far as practicable, it is inevitable that a portion of
the tunnel-emissions will emit via the portals.) The eastern portal will therefore become
an additional point-source. As a
preliminary appraisal, the highest 1-hour NO2 at the Kau Liu/Tin Sam ASR will not be substantially lower than the 246 µg/m³ highest figure for the aforesaid Sha Lo Wan
ASR. In any case, both cases will
be able to meet the AQO limit of 300 µg/m³. At the western portal of Option C, the
air quality impact on the ASR at Sham Wat should not differ considerably to
that of Option A on the ASR at San Shek Wan as the separation distances from
the ASRs for the two options are not different largely, and both cases will be
able to meet the AQO limit of 300 µg/m³ as
well.
(c) The
ventilation shafts for Option C will cause air quality impacts to the Country
Park and the Lantau hillside area, whereas Option A keeps away from the Country
Park and the Lantau hillside completely.
(d) The alignment length of Option A from HKSAR boundary to the Scenic Hill
is about 9.4km which is all in viaduct form, whilst the Option C is about 9.1km
which include ~5.6km viaduct and ~3.5km tunnel. Thus, basically the total emissions from
traffic of both options are more or less the same; except that the emissions
from Option C will be concentrated at the ventilation shafts and the
portals. Comparing the two options,
Option C will require 24-hour lighting and ventilation for the daily operation
of the tunnel and hence more energy consumption which will in turn increase the
emission of greenhouse gases and air pollutants which is not conducive towards
sustainable development; whereas the Option A viaduct (only slightly longer
than Option C) will require only night-time road lightings. Hence, the total air pollutants of
Option C will be greater than that of Option A.
(e) Overall speaking, there should
not be major difference between the two options as regards operation air
quality impact, but Option C will generate more greenhouse gases and air
pollutants due to the tunnel.
(4.1.2) Construction Air
Quality Impact
(a) The
bridgework for Option A will not involve operations generating substantial
amount of dust, whereas the Option C tunnelling work will require extensive
portal-cuttings and processing/crushing of rocks at the portal sites,
generating construction air quality impact in the form of TSP.
(b) Option
A, which does not generate significant TSP in this area, should perform better
than Option C as regards construction air quality impact.
(4.2) Noise
(4.2.1) Operation Noise
Impact –– Similar to the case of 4.1.1, the performance of the two options
should not differ substantially in this regard, because even though the Kau
Liu/Tin Sam NSR is farther away from Option C compared with the distance of the
Sha Lo Wan NSR from Option A, the Option C vent-shafts and portals will in turn
cause noise impacts to Kau Liu/Tin Sam, as well as within the Country Park and
Lantau hillside. Option C is
slightly better than Option A but the difference should not be substantial.
(4.2.2) Construction
Noise Impact –– Similar to the case of 4.1.2, Option A should perform better in
this regard as the bridgework does not involve extensive
percussion/rock-crushing work, whereas Option C does involve such activities as
well as blasting. Option C
also involves transportation of tunnel-excavation materials via
conveyors/chutes from the tunnel-portals onto barges berthed near the Lantau
shorelines at Sham Wat and San Tau, causing additional construction noise
impact.
(4.3) Water
Quality
(4.3.1) Operation Water
Quality Impact –– Though Option A will involve 13 no. pairs of columns in the
water in the Airport Channel, the water quality impact assessment results show
that there will not be any adverse water quality impact (even if more columns
are assumed for conservatism). It is
noted that Option C will involve less columns in the water in the Airport
Channel, for the portion outside the eastern portal across the channel. From an overall point of view. Option C is better than Option A but the
difference should not be significant.
(4.3.2) Construction Water
Quality Impact –– Whilst Option A will involve the construction of more columns
in the water, they are isolated in nature.
Any occurrence of sediment loss from the marine piling works at each
column site will be smaller in scale compared with the dredging works required
under Option C as pointed out in 3.4(e); see also Figure 10 showing the approximate extent of the dredging work. Such dredging works required under
Option C are larger in scale, as a source of water quality impact, than the
isolated columns/marine-piles under Option A. Furthermore, these dredging works as
well as the construction site runoff from the large cutting works of the portal
sites are located in the proximity of Sham Wat Bay and San Tau SSSI, both of
which are ecologically important and sensitive (see Section 4.4 below). It is therefore considered that Option A
does outperform Option C in terms of construction water quality impact.
(4.4) Ecology
(4.4.1) Operational
Ecological Impact –– As shown by water quality impact assessment results in the
EIA Report, Option A will not cause any significant changes in water quality
parameters (such as suspended solids and dissolved oxygen) in the Airport
Channel. The water quality
modelling results in the EIA Report also show that Option A will not cause any
significant change to sedimentation rate in the Airport Channel. Moreover, Option A will not impinge upon
the Lantau hillside at all. Hence
there should be no significant impact on ecology under Option A, neither
terrestrial ecology nor marine ecology.
On the other hand, the eastern and western tunnel portals of Option C
will impinge upon the natural Lantau hillside and shoreline, thus causing the
following ecological impacts (see Figures
6 to 8):
(a) Eastern
Portal (near San Tau)
·
Loss of approx. 1,500m2 woodland and
destruction of approx. 400 nos. of trees.
This woodland is also important for the butterflies in San Tau.
·
At least three species of Protected Plant Species have
been recorded in the eastern portal area.
A rare plant Carex tristachya has also been recorded near the eastern
portal.
·
A rare bird species Emerald dove Chalcophaps indica had also been recorded near the eastern
portal, which is considered vulnerable in China Red Data
Book. The woodland to be impacted
at eastern portal is their major habitat.
·
The nearby San Tau Fung Shui Wood is an important
habitat containing food plant species for butterflies.
(b) Western
Portal (near Sham Wat)
·
Loss of approx. 1.2ha woodland and
destruction of approx. 3,000 nos.
of trees. (Woodland >1ha is considered as
important habitat under Note 2, Appendix A, Annex 6 of EIAO-TM)
·
The western portal is located about 500m to the north
of Sham Wat mudflat, which has been confirmed as one of the horseshoe crab
nursery sites on North Lantau shore.
The dredging works at the western portal may affect the Sham
Wat intertidal mudflat and estuary.
Furthermore, the horseshoe crabs nursery site would be impacted by
Option C, with the workfront brought closer to Sham Wat Bay.
It is obvious that Option C will cause much greater operation ecological
impact (as regards terrestrial and inter-tidal ecology) than Option A.
(4.4.2) Construction
Ecological Impact – The foregoing appraisal on ecological impact for operation
phase is also relevant to that for the construction phase, except that Option C
will cause more construction impact on marine ecology as well (besides
terrestrial and inter-tidal ecology), due to the earthworks and dredging works
required for the portal construction as noted in 3.4(d) & (e). In this regard, both construction site
runoff and dredging locations will cause significant impacts on marine ecology,
as the earthworks and dredging on eastern side will be close to the rare
seagrass species at San Tau SSSI, whereas the earthworks and dredging on
western side will be close to the entrance of the ecologically valuable Sham
Wat Bay (mudflat thereat being the horseshoe crabs nursery site and habitat of
mangroves & intertidal species).
(4.5) Landscape
& Visual
(4.5.1) Operation Phase
(a) As
assessed in the EIA Report, Option A with its viaduct structure in the Airport
Channel will cause moderate impact on VSRs along the
Airport Channel, notably the Sha Lo Wan village,
with mitigation measures.
(b) For
Option C, the tunnel portals will result in extensive cuttings at the scenic hillside as well as damages to the natural coastlines near San Tau and
Sham Wat. The ventilation shaft
within the Country Park may also be a
visual intrusion on the naturalness of the Country Park.
Even if large scale landscape measures are applied, extensive loss of naturalness of the
hillside would be inevitable and visible.
See attached Figures 7 and 8 showing photomontages on the portals, as well as Figure 10 showing photos on completed landscaped portals illustrating the
above. Hence, even though Option C
could obviate the visual impact noted in (a) above, its western portal will cause
moderate visual impact to VSRs in the western waters whilst its eastern portal
will cause moderate visual impact to VSRs at/around the eastern portion of the
Airport Channel.
(c) In
addition, the portal cuttings of Option C tunnel will inevitably damage
~1.3ha woodland and require the felling of approx. 3,400 nos. of trees in
total. The landscape resources (including woodland, shrubland and grassland) and the
landscape character areas (including coastal upland, hillside landscape and the
natural shoreline) around the tunnel portals will be affected.
(d) Overall
speaking, Option C will not perform better than Option A from
landscape & visual point of view at operation phase. In particular, it should be
noted that Option C will cause damage to the natural hillside
and shoreline, whereas Option A will not.
(4.5.2) Construction
Phase –– As shown in the photos on Figure
9, the construction of land tunnels will require extensive site
installations at portal areas.
Also, the landscape impact described in 4.5.1 above applies to both
operation phase and construction phase.
The conclusion in (a) on operation phase is applicable to construction
phase too.
(4.6) Cultural
Heritage
(4.6.1) For both
operation and construction phases, Option A will perform better than Option C
as regards Cultural Heritages, as the former will not touch the Lantau area
whereas the latter will affect the Tung O Ancient Trail (see attached Figure 6).
(4.7) Waste
Management
(4.7.1) Operation Phase
–– No difference between the two options as regards waste management.
(4.7.2) Construction
Phase –– Option A will perform better than Option C as regards waste
management, as the latter will involve a tunnel which will generate approx. 2Mm³
of waste materials. In addition,
Option C will involve seabed dredging as well.
(4.8) Conclusion
(4.8.1) The comparison
between Option A and Option C on various environmental aspects as explained in
the foregoing section is recapitulated below:
Environmental Aspect |
(✔ denotes the option with
better performance) |
||
Option
A |
Option
C |
||
Air |
Operation |
(No
substantial difference but Option C will increase greenhouse gases emission
due to the tunnel) |
|
Construction |
✔ |
|
|
Noise |
Operation |
|
✔ |
Construction |
✔ |
|
|
Water |
Operation |
|
✔ |
Construction |
✔ |
|
|
Ecology |
Operation |
✔ |
|
Construction |
✔ |
|
|
Landscape & Visual |
Operation |
(No
substantial difference) |
|
Construction |
(No
substantial difference) |
||
Cultural Heritage |
Operation |
✔ |
|
Construction |
✔ |
|
|
Waste |
Operation |
– |
|
Construction |
✔ |
|
(4.8.2) In view of the
above, it should be concluded that the overall performance of Option A is
better than that of Option C from environmental points of view.
[1] The water
quality assessment of the EIA of HKLR has in fact assumed more columns in this
portion of HKLR (16 pairs in lieu of 13 pairs). This is for conservatism. In fact the water quality assessment
results show that even with the larger number of columns, there will not be any
adverse water quality impacts.